Maintenance and commissioning of industrial boilers

Start / Case studies

Revamping, Economy

Project

Description

 

Revamping of two fire tube boilers, steam production 20t/ha at 15 bar pressure.

Work Completed:

Installation and testing of the combustion gas temperature regulation system with activation of the heat recovery unit in the chimney.
Activation of Remote Monitoring System (Opticloud).

Challenge:

Reduction of the temperature of the combustion gases, while increasing the temperature of the feedwater, to increase the efficiency of the boiler and reduce gas consumption.

Success:

Positive result of the intervention, achieving an efficiency of 96% with a combustion gas temperature of 105ºC, compared to the previous values of 155ºC and an efficiency of 94%

Customer

Biofuel

Location

Cartagena, Spain

Service

Revamping, Economy

Year of the project

2025