Steam boilers, 20 t/h, 15 bar pressure + superheated water heat exchanger
Work completed:
Generator testing has been completed, including verification of safety and control systems, combustion curve adjustment, and functional and performance testing.
The commissioning process to configure and optimize all adjustment and operating parameters has been completed.
Success: positive, the heating network works in automatic temperature control.